REFORM · CUSTOM FABRIC DEVELOPMENT

A thread from idea to delivery.

Follow the material journey as a custom fabric moves from the first brief, through development and production, into a finished uniform ready for delivery.

102–110 daysEstimated total lead time when each stage runs sequentially and approvals remain on schedule.

3 days

Material brief

Define the required look, feel, weight, performance, fibre composition, certifications, volume and target cost.

7–10 days

Lab development

Develop the fabric construction and technical specification, then prepare the first laboratory trial for review.

10 days

Fabric sampling and approval

Produce and review the fabric sample, confirm its hand feel and performance, and approve it for bulk development.

7 days

Garment sampling

Create a garment sample in the selected fabric to assess fit, drape, construction and overall appearance.

30 days

Bulk fabric production

Manufacture the approved fabric construction in the confirmed bulk quantity and complete initial quality checks.

10 days

Fabric dyeing and treatments

Apply the approved colour, finishes and performance treatments, followed by shade and finish inspection.

15–20 days

Uniform production

Cut, manufacture, finish and quality-check the approved uniform range, including branding and custom details.

10–15 days

Delivery

Pack the completed order according to project requirements and coordinate transport to the final destination.

Ready to deliver.

The thread completes its journey as finished uniforms—quality checked, packed and prepared for the client.

Indicative timing begins after the project brief and commercial terms are confirmed. Revisions, testing requirements, order volume, fibre availability, public holidays and shipping conditions may affect the programme. Existing stock fabrics follow a shorter timeline.